
Citicore Holdings Investment Inc. (CHII) has built a nearly P1-billion direct position in Citicore Renewable Energy…

The Department of Justice (DoJ) affirmed its decision Tuesday to prosecute Vice President Sara Duterte on three counts…

The Bureau of Customs (BoC) stressed Tuesday that it remains committed to its partnership with the Philippine National…

National Cinema Day promises a one-day-only surprise as cinema stakeholders unite to bring Filipinos back to the big…
The Department of Migrant Workers (DMW) on Tuesday said that 261 out of 400 Filipino seafarers were safely repatriated…
Energy regulators are pressing for the on-time completion of the P5.27-billion Nabas-Caticlan-Boracay Transmission Line Project (NCBTLP) to ensure an uninterrupted domestic power supply amid persistent global energy uncertainties.
The Department of Energy (DOE), together with the Energy Regulatory Commission (ERC), National Transmission Corp. (TransCo), and National Grid Corp. of the Philippines (NGCP), conducted a site inspection of the project early this week as oversight tightens ahead of its completion.
In a statement on Thursday, Energy Undersecretary Rowena Cristina L. Guevara said regulators will ensure the project’s delivery by August, with completion now at 93 percent.
“We are fast-tracking the completion of this critical project because reliable power is fundamental to economic growth, public service, and the continued development of Boracay and the rest of Aklan,” Guevara said.
“Our inspection confirms that substantial progress has been made, and the Department remains fully committed to ensuring that this infrastructure is completed on schedule and built to the highest standards of safety, quality, and long-term reliability.”
Key components have already been completed and energized, including the Nabas Substation, the rehabilitated Unidos-Caticlan Transmission Line, and the Caticlan 69-kilovolt XLPE Cable. Grid adjustments finished in December 2025 have also helped reduce outages caused by environmental factors.
Remaining works are in advanced stages, with most transmission lines and cable systems nearing completion, while the Boracay GIS Substation and underground cable installations continue to progress.
Underground works are being carried out at night to meet aviation safety requirements, with completion targeted by June 2026.
Once completed, the project is expected to provide more reliable power to over 155,000 households, 13,000 businesses, and 27 industrial users in Aklan.