Stalled Naga Convention Center probe sought

An anti-corruption group has asked the Office of the Ombudsman to investigate the stalled construction of the Naga City Convention Center in Barangay Carolina, Naga City, Camarines Sur, citing questions over project funding, implementation and ownership of the site.
The Philippine Anti-Corruption Czar (PACC) said the project was supposed to receive about P600 million in funding over several years, but only P98.69 million was allocated for its first phase in 2023.
PACC founder and chairman Louie Ceniza said the group inspected the site and found signage suggesting that the property was privately owned.
“We filed a complaint here at the Ombudsman so the Ombudsman will conduct its own investigation on those who were involved in the Naga Convention Center,” Ceniza said.
“The Naga City Convention Center should have been accomplished this year, if the construction was not stopped,” he added.
The group asked the Ombudsman to order a technical, engineering and structural audit to determine whether the project complied with plans approved by the Department of Public Works and Highways (DPWH).
It also sought an investigation into possible irregular expenditures involving the agency and contractor Centerways Construction and Development Inc.
Geotagging error
Ceniza said funding for the project was supposed to be included in the 2026 budget but was held up by an error in the project’s geotagging.
“This year, there was a budget for the Convention Center but the problem was, the DPWH said that it had erred in geotagging. There was a five-kilometer discrepancy on the geotagging, from Naga City it was tagged in Pili,” he said.
PACC asked the Ombudsman to consider filing charges against officials of the DPWH Camarines Sur 3rd District Engineering Office and the contractor for alleged violations of Sections 3(e) and 3(g) of the Anti-Graft and Corrupt Practices Act.
The complaint included documents signed by the Naga City Council, the property owner and former Mayor Nelson Legacion.
DPWH records identified the project as the “Multi Purpose Building Convention Center in Carolina, Naga City Phase 1.” The P98.69-million contract was awarded to Centerways on 22 December 2023, took effect on 9 January 2024 and was listed as completed on 7 April 2025.
The project was funded under the 2023 General Appropriations Act through the DPWH Convergence and Special Support Program.
Among the bidders was St. Gerrard Construction General Contractor & Development Corp., owned by Sarah and Curlee Discaya. Both St. Gerrard and Centerways were among the 15 contractors identified by President Ferdinand Marcos Jr. as involved in the multibillion-peso flood control controversy.