Construction history
Construction began on 23 October 1930 and was expected to be completed within 240 days. The project was undertaken because, according to the Bureau of Public Works, “the present one has been found inadequate for the needs of the community.” The old municipio was most likely located near the town plaza.
Gregorio Malinis of Lucena Ciity served as contractor for the new building under a P59,500 contract. The government supplied him, free of charge, with 1,100 barrels of tested cement for its construction. The project’s total allocation was P80,000, funded through a loan from the Insular Government. Of this amount, P2,000 was set aside to purchase the site.
The property was most likely owned by the Rodriguez family, who also owned the adjacent grand American-era residence now known as the Emralino-Rodriguez Ancestral House, or simply the Pink House.
By the end of 1930, the building was reported to be 15 percent complete.
Originally scheduled for completion on 20 June 1931, the municipio was officially completed on 3 July 1931, during the term of municipal president Hilarion Valderas.
Federico Ilustre
In the postwar years, two two-story wings were added to accommodate Sariaya’s growing needs and the municipal government’s expanding offices and services. The additions, designed in sympathy with the Art Deco character of the original building, were executed by Federico Ilustre, then consulting architect of the Bureau of Public Works.
Among Ilustre’s other works are the Government Service Insurance System Building and the now-demolished Veterans Memorial Building on Arroceros in Manila, as well as the Philippine Coconut Authority Building and the Quezon Memorial Monument in Quezon City.
In the 1960s, the municipio underwent repairs during the administration of Mayor Andres Remo. The restored building was inaugurated on Bonifacio Day in 1963.
The old municipio is now largely unoccupied following the construction of the new Sariaya Municipal Hall, located about a kilometer southeast of it. The new building was inaugurated in November 2025.
Only the post office, library, Regional Trial Court and Office of Senior Citizens Affairs remain in the old building, which the local government and the DPWH plan to restore.
Restoration will proceed once the relevant cultural agencies approve the development plans to be submitted by the local government. Upon completion, the building will house a museum and a revitalized public library.