Under the pipeline, Panay could gain 135 MW of baseload capacity by 2028, another 270 MW in 2029 and 150 MW in 2030.
More flexible generation
The region could also receive 220 MW of gas-fired mid-merit capacity by 2028, providing more flexible generation that can respond to swings in electricity demand and supply.
Combined, the projects would provide 775 MW of additional capacity through 2030 to support households, businesses, industries, and future investments in Western Visayas.
The DoE is also advancing the Mindoro-Panay Interconnection Project, which is expected to strengthen Panay’s access to power from outside the region.
Once completed, the project will connect the Visayas Grid to the transmission link between Batangas and Mindoro, creating another connection between Luzon and the Visayas.
The link is expected to give the grids greater flexibility to transfer available electricity during tight supply conditions and generation outages.
“Securing Panay’s energy future requires us to address today’s supply constraints while building the generation and transmission infrastructure that Western Visayas will need in the years ahead. This is a shared responsibility and strong stakeholder support is vital to delivering stable electricity, driving economic growth and improving the lives of every Filipino in Region VI,” Garin said.