CoA flags P2.56-B Cebu water projects

CoA flags P2.56-B Cebu water projects

COA

Text size

The Commission on Audit (CoA) has flagged about P2.556 billion in bulk water projects implemented under the previous administration in Cebu province, reporting that only one of 16 projects was operational.

In its 2025 Annual Audit Report, state auditors said only the P56.88 million Moalboal Bulk Water Supply Project was running, while the province had already paid P879.42 million to contractors — including P822.44 million paid to 15 contractors for undelivered works.

Auditors attributed the stalled rollout to terminated or suspended contracts, incomplete water sources, missing permits, lack of electricity, right-of-way and land disputes, and unfinished facilities.

Also read Ilocos Norte provides nearly P100M in farm, fisheries assistance

In Santander, a waterworks project completed on 31 December 2023, remained without water to distribute more than two years later.

Alcoy faced a similar water-supply hurdle tied to neighboring Boljoon, where auditors found two unfinished water tanks, an incomplete treatment plant and rusting steel reinforcements.

In Barili, construction on the Cluster B project was completed, but the provincial engineering office struggled to secure a permit from the National Water Resources Board amid a usufruct agreement issue over the treatment plant site.

In Malabuyoc, inspection showed the project was 86.77 percent complete with treatment and distribution structures in place, but the plant lacked electricity.

Work was suspended in San Fernando and Dalaguete, where some pipes were installed in mountain villages while others remained in a contractor’s storage yard.

Five contracts covering projects in Argao, Boljoon, Barili, Alegria and Samboan had been terminated or were facing termination proceedings.

In Argao, pipeline work halted following delays that led to contract termination, leaving unfinished structures at the water source and a partially built concrete tank.

Alegria stood at 18.59 percent completion with water tanks installed, but its treatment facility remained unfinished and distribution pipes lay exposed.

Auditors also reported unfinished or unsecured components in Barili, Moalboal, Oslob and Tabogon.

The commission called for a review of all 16 projects funded from the province’s 20 percent development fund, urging the provincial engineering office and the provincial planning and development office to assess which facilities can be placed into service, set timelines for each and prioritize completed or nearly completed works.