Evenly split supply requirement
GMEC, meanwhile, initially offered the entire 600-MW requirement at P5.5789 per kWh before reducing its offered capacity to 200 MW, allowing the three lowest bidders to evenly split the supply requirement.
All offers were inclusive of value-added tax and a capped line rental charge.
The auction gives Meralco a clearer line of sight on its baseload supply beginning in 2028, while the competitive bids could help contain generation costs passed on to customers once the contracts take effect.
The resulting power supply agreements will run for 15 years, with the first 300 MW targeted for delivery by 26 February 2028 and the remaining 300 MW beginning 26 February 2029.
The three offers emerged from a field of six bidders that submitted qualification documents, technical proposals, and bid prices by the 1 September deadline. Nine companies had initially expressed interest in joining the CSP.
Masinloc Power Co. Ltd. offered P5.6290 per kWh for 200 MW, while Therma Luzon Inc. submitted a bid of P5.6988 per kWh for 194 MW.
Except for Energy Development Corp., all offers received were below the reserve prices set for the CSP, according to Meralco’s Bids and Awards Committee for Power Supply Agreements (BAC-PSA).
All submissions underwent a pass/fail completeness assessment and pre-qualification evaluation.
“The Meralco BAC-PSA has fully complied with its mandate to conduct the bid in an open and transparent manner to achieve the least cost of electricity in accordance with rules and regulations set by the Department of Energy and the Energy Regulatory Commission (ERC),” Meralco BAC-PSA chairman Lawrence S. Fernandez said.
The bidding was witnessed by consumer groups and representatives of the Philippine Competition Commission, while the proceedings were also streamed live on Meralco’s YouTube page.