Mindanao Container Terminal expansion in full steam as cranes arrive

MINDANAO Container Terminal’s four new hybrid RTGs are positioned in the container yard for installation and commissioning to support container handling operations.
PHOTOGRAPH COURTESY OF ICTSI
The expansion of Mindanao Container Terminal (MCT) is in full steam as Mindanao International Container Terminal Services Inc. (MICTSI), a subsidiary of the International Container Terminal Services Inc. (ICTSI), received the delivery of four hybrid rubber-tired gantry (RTG) cranes three months ahead of schedule.
Aurelio C. Garcia, MICTSI chief executive officer, said the RTGs’ arrival mark an important step in the MCT’s expansion.
Garcia said the arrival of the new RTGs highlights the progress being made across MCT’s expansion program: “While we’ve seen construction progress over the past several months, seeing the first RTG arrive and be discharged was a significant moment for the project. It reflects the progress being made across the terminal and the work that continues behind the scenes.â€
“We formalized the project in late 2024 and established a clear timetable. I’m pleased to say that everything remains on schedule,” he said.
MCT is expanding capacity to meet rising cargo demand and support northern Mindanao trade. The expansion also includes a 300-meter berth extension, orders of three post-Panamax quay cranes, expansion of reefer facilities, and additional container storage capacity.
Construction of the berth extension is progressing, with the first 120 meters targeted for completion by the end of the first quarter of 2027. The first of three new post-Panamax quay cranes is expected to arrive shortly afterward and will become operational following commissioning. Once completed, the initial phase will increase MCT’s operational berth length to 420 meters, providing additional capacity for vessel calls and shipping services.
Meanwhile, expanding the terminal’s reefer facilities aims to accommodate increasing volumes of refrigerated import and export cargo, while work is underway to expand the empty container depot and increase container storage capacity.
Supporting infrastructure projects include the construction of a new electrical substation that will provide the power required for additional equipment and future operational needs.
Located within the Phividec Industrial Estate, MCT serves as Northern Mindanao’s primary international container gateway. The terminal supports the movement of import and export cargoes and helps connect businesses across the region with domestic and international markets.
The current phase forms part of MCT’s long-term expansion program, which is scheduled for completion in the first quarter of 2028. By then, MCT is expected to complete the full 300-meter berth extension and commission all three quay cranes.
“With additional berth capacity becoming available next year, we expect to be in a stronger position to accommodate more vessel calls and support additional shipping services,” Garcia said. “We look forward to completing the program on schedule and continuing to build on MCT’s role in supporting trade and industry in Mindanao.”