Friday, 7 August 2026
Nasdaq -0.06%
Subscribe NowSupport Us

Daily Tribune

Daily Tribune
Subscribe
Friday, 7 August 2026
  • News
  • Opinion
  • Business
  • Life
  • Show
  • Sports
  • Global Goals
Partner feature

The Philippines' leading digital newspaper.

News
  • Headlines
  • Page three
  • Metro
  • Nation
  • World
  • Dyaryo Tirada
  • Obituary (Remember Me)
  • SONATOTOO (archive)
Opinion
  • All columnists
  • Editorials
  • Guest essays
  • Letters to the Editor
  • Scuttlebutt
Business
  • Shipping
  • Portraits
  • Pep
  • Business Advisories
  • Technology (Tech Talks)
Life
  • Show
  • Food & Drink
  • Getaways
  • Arts & Culture
  • Social Set
  • Spaces
  • Fashion & Beauty
  • The Edit
  • Top Form
  • Next Gen
  • Sacred Space
  • Project Larawan
  • Snaps
Sports
  • Hoops
  • Volley
  • Golf
  • Goal
  • Boxing
  • Tennis
  • Esports
  • Blast

Company

  • SONATOTOO archive
  • About
  • Contact
  • Advertise
  • Privacy
  • Subscribe
  • Support Us

© 2026 Daily Tribune · tribune.net.ph · Powered by Quintype

NEWS

Sandro-linked P28.5-M bridge goes nowhere

Jason Mago·1 January 2026, 12:06 am·1 MIN READ

Sandro-linked P28.5-M bridge goes nowhere
Text size
Partner feature

Stay informed

Get Daily Tribune in your inbox

Breaking news, opinion, and business coverage for readers in the Philippines and abroad.

Subscribe to the newsletter

Read next

Over ₱32M in agricultural aid distributed to Ilocos Norte farmers

Over ₱32M in agricultural aid distributed to Ilocos Norte farmers

What's your take?

Share

Google Preferred Sources

Get more Daily Tribune stories in your search results

Add Daily Tribune as a preferred source on Google Search.

Add to Google

Continue reading

  • Smoke, mirrors commission
    Smoke, mirrors commission
  • Ping: Alan dodging Taguig issue
    Ping: Alan dodging Taguig issue
  • FIFA certifies sports hub
    FIFA certifies sports hub
Partner feature
Partner feature
Partner feature

Suggested Articles

World Bank nods $250-M loan for Bohol, Siargao, Jolo water projects
BUSINESS

World Bank nods $250-M loan for Bohol, Siargao, Jolo water projects

The World Bank has approved a $250.87 million loan to expand climate-resilient water and sanitation services in Bohol,…

Toby Magsaysay·3 August 2026

Romualdez camp says Co bodyguard claims unreliable, urges fair probe
NATION

Romualdez camp says Co bodyguard claims unreliable, urges fair probe

One of the lawyers of former House Speaker Martin Romualdez said their client is seeking only fairness in the ongoing…

Jerod Orcullo·2 August 2026

Ilocos Sur student found dead beside motorcycle
NATION

Ilocos Sur student found dead beside motorcycle

A 21-year-old student was found dead beside his motorcycle along a farm-to-market road in Barangay Capangdanan, Bantay,…

Jasper Dawang·2 August 2026

Marcos takes dev’t agenda nationwide
HEADLINES

Marcos takes dev’t agenda nationwide

President Ferdinand Marcos Jr. followed his fifth State of the Nation Address (SoNA) with a series of regional…

Raffy Ayeng·2 August 2026

23,000 marijuana plants destroyed
NATION

23,000 marijuana plants destroyed

The largest operation was a marijuana eradication campaign in Sugpon, Ilocos Sur.

Jasper Dawang·1 August 2026

Share

In Barangay Cabaroan, in Ilocos Norte, what rises from the river is not a bridge but a row of concrete foundations, an outcome that exposes deep flaws in how a P28.46-million public works project was planned, packaged, and rolled out in a district represented by Ferdinand Alexander “Sandro” Marcos.

Contract 25AA0294, officially titled Construction of Cabaroan–Libnaoan Bridge, covers only 10 sets of bored pile foundations. The works were completed and paid for. Still, they delivered no crossing, no access, and no immediate benefit to the residents who continue to ford the river or take a detour to reach the next barangay.

On the ground, exposed columns and steel reinforcement are embedded in the riverbed. There is no deck, no span, and no approach road, only a substructure intended to support a future bridge that does not yet exist.

Bridge can’t be crossed

Under the Government Procurement Policy Board’s rules, infrastructure projects may be implemented in stages. Still, programming is intended to either deliver a usable portion or clearly demonstrate assured continuity toward a functional facility.

In this case, the foundations-only phase delivers zero public utility. Available documents reviewed by DAILY TRIBUNE do not identify a succeeding contract, a timetable, or a multi-year funding authority that would guarantee when the actual bridge deck and approaches will be built.

DPWH-linked sources said the project is part of a multi-year plan. One source said the indicative budget for Phase 2 — covering the superstructure and approaches — could reach around P50 million, with 2026 as the target year. No public document, however, confirms the funding, nor does any show that it has been programmed or secured. The source called it a “confidential document.”

Funds out, certainty absent

Records showed the contractor, North Tech Builders and Construction Supply, has received about P25.6 million, or roughly 90 percent of the contract amount, with standard retention accounting for the balance.

DPWH officials maintain the contractor delivered in accordance with the contract specifications.

The larger question, however, is whether a project procured and presented as a bridge should have been broken into a foundations-only package without publicly demonstrating continuity to completion, an outcome procurement safeguards were designed to prevent.

Political links sharpen scrutiny

Scrutiny has intensified because of the contractor’s political connections.

An earlier investigation by Rappler identified North Tech as the third-largest DPWH contractor in Piddig, Ilocos Norrte, since 2016, with P72.3 million worth of projects in the town. The firm is owned by Maribeth Salazar, wife of Piddig Vice Mayor Edwin Salazar and sister-in-law of Eddie Guillen.

Guillen is the current administrator of the National Irrigation Administration (NIA), having been appointed by President Ferdinand Marcos Jr. His office has denied any involvement in the procurement, citing the Department of Public Works and Highways’ (DPWH) decentralized bidding process.

Governance analysts cited by Rappler noted that conflicts of interest do not always appear in signatures, particularly when contractors linked to political families repeatedly secure projects in their own jurisdictions.

Not illegal, yet deeply flawed

There is no clear evidence that procurement rules were violated in the contract award. But policy weaknesses are harder to ignore.

A project bid out and labeled as a bridge delivered only the substructure, produced no usable portion, and now points to a much larger follow-on cost to complete what residents believed they were already getting.

The Cabaroan–Libnaoan project is officially recognized. It is not fictitious. But it is also not a bridge. What stands instead is a costly first act, with the ending deferred to another year, another budget, and another set of approvals.