Cebu-Bohol 230-kV power link done in 2024


The National Grid Corporation of the Philippines has announced that the Cebu-Bohol 230-kilovolt interconnection project will be completed in 2024.
In a virtual energy investment forum, Michael R. Baylosis, head of the Visayas System Planning Division of NGCP, said "Right now, we have completed the laying of the submarine cable, and we are working towards the completion of the substation and transmission lines. So, the target is by next year, 2024."
Option 1
The Energy Regulatory Commission has approved Option 1 of the NGCP's proposed project valued at P19.61 billion.
The Cebu-Bohol interconnection project connects the two islands via double-circuit 230-kV submarine cables.
Three decades after the Marcopper mining disaster devastated Marinduque’s waterways, the province is again pressing the…
Housing is probably the biggest issue affecting people the world over.
Malacañang on Monday called for a more thorough investigation into the questioned flood control projects in Taguig…
The defense on Monday backed the move by senator-judges to exclude a prosecution witness who testified on the firearms…
The link will head off overloading of the Leyte-Bohol 138-kV submarine cable and provide Bohol island with another source of power.