Cebu-Bohol 230-kV power link completion seen in 2024



President Donald Trump on Wednesday announced a $22.5 billion overhaul of Washington Dulles International Airport,…

PALO, Leyte – School authorities confiscated a short firearm from a Grade 6 learner who brought it to school in…

The National Irrigation Administration–Ilocos Norte Irrigation Management Office (NIA-INIMO), in partnership with the…

Police arrested five wanted persons facing various criminal charges and apprehended a fisherman for violating a…

Police arrested three suspected drug personalities and seized illegal drugs worth an estimated P11,628 in separate…
The National Grid Corporation of the Philippines announced the Cebu-Bohol 230-kilovolt interconnection project will be completed in 2024.
In a virtual energy investment forum, Michael R. Baylosis, head of the Visayas System Planning Division of NGCP said " Right now, we have completed the laying of the submarine cable, and we are working towards completion of the substation and transmission lines. So, the target is by next year,2024."
The Energy Regulatory Commission approved Option 1 of NGCP's proposed project valued at P19.61 billion.
The Cebu-Bohol interconnection project connects the two islands via double-circuit 230-kV submarine cables.
The link will head off the overloading of the Leyte-Bohol 138-kV submarine cable and provide Bohol Island with another source of power.