Maynilad hikes water storage, spends P1.07B
Expansion of Bagbag Reservoir involves the construction of a new chamber in this underground reservoir, which will add another 100 million liters to its storage capacity
Expansion of Bagbag Reservoir involves the construction of a new chamber in this underground reservoir, which will add another 100 million liters to its storage capacity

As DigiPlus Interactive Corp. scales up its international expansion, the company has joined the Brazilian Institute of…

Finance Secretary Frederick Go announced that MySSS Card holders can avail of a two-week PISO Fare promotion as the…

The Philippine Stock Exchange Index (PSEi) fell 9.70 points, or 0.15 percent, to 6,256.02 on Tuesday, while the peso…

President Ferdinand Marcos Jr. extolled the MVP Group for investing in its Meralco Terra Solar Project in Nueva Ecija,…

Four years after ending nickel mining operations, Berong Nickel Corporation (BNC) is investing heavily in restoring its…
Read next
What's your take?
Google Preferred Sources
Get more Daily Tribune stories in your search results
Add Daily Tribune as a preferred source on Google Search.
West Zone concessionaire Maynilad Water Services Inc. has earmarked P1.07 billion to augment the storage capacity of its main reservoir in Quezon City to address water supply constraints.
Maynilad has 39 reservoirs across its franchise area, but the Bagbag Reservoir, which can store up to 200 million liters of treated water produced by its La Mesa Treatment Plants 1 and 2, serves as its primary reservoir.
It serves around 4 million customers in Quezon City, Caloocan, Malabon, Navotas, Manila, Makati, Pasay, and parts of Parañaque and Cavite — representing approximately 58 percent of Maynilad's total customer base.
Maynilad said the expansion of Bagbag Reservoir involves the construction of a new chamber in this underground reservoir, which will add another 100 million liters to its storage capacity.
Service improvements done
Likewise, the water company said other enhancement works on the facility, including a 1,800 mm-diameter inlet and outlet pipeline installation, new tank construction, and pump upgrade to improve its operating capacity.
"Water demand has been increasing over the years due to population growth in urban areas."
"By increasing our water-storage capacity, we can address availability issues, especially during hours of peak demand when consumption can sometimes exceed our water reserves," Maynilad president and CEO Ramoncito Fernandez said.
Based on the latest timeline provided by the company, the project is scheduled to be completed by 2027.