HEADLINES

No dry faucet starting 2025

The Wawa Bulk Water Supply Project aims to ensure sufficient capacity to meet the Metropolitan Waterworks and Sewerage System’s and its concessionaires’ water needs

Maria Bernadette Romero

Metro Manila's perennial water supply woes are expected to end in 2025 when the Upper Wawa Dam, the second phase of the Wawa Bulk Water Supply Project, which is now 70 percent completed, will be finished.

WawaJVCo Inc., led by Prime Infra, said the pivotal project remains on schedule to start commercial operations by 2025.

The Razon infrastructure flagship said the 85-meter roller-compacted concrete dam is expected to be finished in a few months, followed by the completion of the rest of the plant.

"The Wawa Bulk Water Supply Project aims to secure sufficient capacity to meet the Metropolitan Waterworks and Sewerage System's and its concessionaires' water needs. Phase 1 became operational in record time in October 2022," Prime Infra president and CEO Guillaume Lucci said.

Once operational, the dam will have a yearlong water supply capacity of over 700 million liters per day, or MLD. to benefit the residents of the greater Metro Manila area, including the province of Rizal.

Apart from providing a reliable water source, the Upper Wawa Dam will also help mitigate the perennial flooding problem downstream of the Marikina River.

Flagship project

Phase 2, or the Upper Wawa Dam, will deliver over 700 MLD of water by the end of 2025. The project's first phase, or the Tayabasan Weir, has been delivering an initial 80 MLD since it began operations.

"The exceptional construction pace at Upper Wawa Dam showcases Prime Infra's commitment to delivering on our commitments in developing water supply infrastructure at this scale. We are pleased that the project continues to be materially ahead of schedule. We take great pride in ensuring that we can sustain this pace and do so safely by 2025," Lucci said.

The Wawa Bulk Water Supply Project in Rizal is one of the national government's flagship infrastructure projects that will address water security, specifically in the MWSS service area.

The project is the largest water supply dam to be constructed in over 50 years after the Angat Dam. It will increase Manila Water Co.'s capacity by over 30 percent of its current water supply allocation from the Angat Dam of approximately 1,600 MLD.

WawaJVCo is also implementing a watershed management plan that includes reforestation around the site of the Wawa Bulk Water Supply Project covering 1,800 hectares.

Eco-tourism park slated

"We were able to secure the necessary permits and most importantly, obtain the seal of approval for the social aspects of the project to demonstrate the capability to deliver not only critical water infrastructure but also provide economic upliftment of local communities and environmental conservation," Lucci said.

"We are developing the master plan to make Wawa an eco-tourism site that will provide a long-term positive impact to them," he added.

 Tayabasan has three parts including the weir, where water is impounded; the pumping station that brings the bulk water to the treatment plant; and the buried water pipeline, where the bulk water passes to get to the water treatment plant.

WawaJVCo obtained the approval of the Dumagat/Remontado Indigenous People of Antipolo and Rodriguez for the Upper Wawa Dam. It was the project's fourth and final Memorandum of Agreement in the Free and Prior, Informed Consent, or FPIC, process.

WawaJVCo received the Certificate Precondition from the National Commission on Indigenous Peoples, certifying that the FPIC Process has been complied with by the company and the communities gave their consent to the project.