Jeffrey G. Damicog · Nov 18, 2026, 11:25 PM

COLLAPSED girders lie at the construction site of the ongoing P512-million Gandara Parallel Bridge project in Gandara, Samar, following a structural incident on Tuesday. The two girders gave way while workers were removing a roller attachment, prompting authorities and local engineering units to assess the damage and review on-site safety protocols. — Screengrab from Edwin Mañozo/DPWH/FACEBOOK

A contractor could face severe penalties over the collapse of two girders at the ongoing Gandara Parallel Bridge project in Samar, the Department of Public Works and Highways (DPWH) said Wednesday.

The incident occurred Tuesday during the removal of a roller attachment at the P512-million bridge construction project.

“The DPWH assures the public that the contractor will face severe penalties if technical assessments reveal that the collapse was due to defects in construction,” the department said.

DPWH Secretary Giovanni Lopez has ordered the mobilization of a technical team to assess the incident and determine the appropriate corrective measures needed to ensure the project’s safety and proper implementation.

The department also assured the public that it would comply with President Ferdinand Marcos Jr.’s instructions to prioritize the safety of workers at the construction site.

So far, the contractor has reported that no workers were injured in the incident.