GEAP-backed solar plant comes online in Mindanao

Maria Bernadette Romero · Jul 24, 2026, 3:14 AM

A utility-scale solar power project backed by the government’s Green Energy Auction Program (GEAP) has begun supplying electricity in Mindanao, expanding the island’s renewable energy capacity and strengthening power supply for about 68,000 households.

The Department of Energy (DoE) on Thursday energized Phase 1 of the Tantangan Solar Power Project in Sultan Kudarat, a 99-megawatt-peak (MWp) facility being developed by Apolaki Seven Inc. and IbVogt under the GEAP.

The newly energized Phase 1 delivers 74.5 MWp and marks a key milestone for the project, which is now 97.3 percent complete. The remaining capacity is scheduled for completion by October, bringing the facility’s total installed capacity to 99 MWp.

Reliability of Mindanao’s electricity supply

Energy Secretary Sharon S. Garin said the project will improve the reliability of Mindanao’s electricity supply while supporting the country’s push to reduce dependence on imported fuel.

“By bringing utility-scale solar generation to Mindanao, this plant strengthens the reliability and diversity of the island’s power supply. Amid the Middle East conflict, we are on a mission to reduce the Philippines’ dependence on imported sources and generate our own electricity,” Garin said.

Once fully operational, the project will generate about 163 gigawatt-hours of clean electricity annually and avoid around 113,950 metric tons of carbon emissions each year.